| 12 months |
- establish the move's in-house management team, and
- retain an architectural firm who will analysis of amount and type of space that you need
|
| 11 months |
- retain a Real Estate Broker,
- have your architect prepare conceptual space plans for the alternate locations,
- select and secure the initial commitment for the new location
|
| 10 months |
- review offices systems, phone, communication,
- prepare an inventory of existing furniture to be used
|
| 9 months |
- sign the new lease
- request that your architect develop the conceptual space plan
|
| 8 months |
- architect to develop the approved design
|
| 7 months |
- architect to complete the construction drawings, finish selections and furniture selections
- select a general contractor and apply for the building permit
|
| 6 months |
- select furniture dealership and order new furniture
|
| 4 months |
- start construction
- select a moving company,
- coordinate stationary, phone changes
|
| 1 month |
- coordinate the move's final details ,
|
| moving day |
- start move on Friday,
- start work in new space on Monday,
- start the moving team's vacation - they will have earned it!
|